The second phase of the construction of Bosmansdam Road commenced today.
The project is scheduled to take eight months to implement and it’s expected to be complete by July 2020.
The first phase was implemented between April 2018 and July 2019.
While Phase 1 entailed the construction of the Eastbound two-lane carriageway, Phase 2 will seek to rehabilitate the existing westbound two-lane carriageway between Koeberg Road and Montague Drive.
Traffic will be affected in both directions as only a single lane on the portion of the current westbound carriage way of Bosmansdam Road will be open during the construction period.
Ocean Spirit to Ratanga Road will be closed from mid November 2019 to end January 2020 while Ratanga Road to Koeberg Road will be closed from February 2020 to July 2020.
During these closures, vehicles will have a two-way flow on the recently completed Eastbound carriageway with adjusted traffic signals and the required deviation signage along the route.